Windows!
I didn't make it out to the construction site last week (other fish to fry) so this week was a fun visit.
Many of the windows were in, the rest are on site and should be installed before Thanksgiving.
The house is wrapped (almost done).
The plumbing is mostly done (rough-in stage).
The roof is mostly done (enough to "dry in" for the winter and as far as they can go without the post and beam materials).
The fireplace rough in is started.
The entry hall closets were roughed in this time.
And, during this visit, I met with the electrician.
If I don't report in again beforehand, Happy Thanksgiving.
Master Bedroom Dining Room Standing in the pantry looking through the house Standing by the fireplace looking toward the pantry The Living Room (windows) Fireplace being roughed in Master Bath (window) Windows in the closet!